Welcome to the Blake Block web page. Visit often to get the current status of the construction.
April 28 - Start of utility pole removal prep work. T-minus 2 months & counting for projected building completion. Beautiful one- and two-bedroom residential condos for sale on 2nd floor.
For information on premier retail/restaurant space leasing, contact Bruce Blake at 781-492-2743.
April 21 - Another week of beautiful weather & lots of colorful clapboard applied. Progressing by leaps and bounds now!
April 7 - Pole Capping Day & brick front is nearly done with decorative tiles salvaged from old block inlaid around the bend.
March 30 - Brick work, siding, and roofing continues, plus the addition of the corner stone and new signage in front.
March 11 - Spring is around the corner - more windows & doors have been installed - really shaping up!
March 1 - There may be snow outside, but things are moving along inside!
February 18 - More windows, some brick work, and inside framing. It's really coming along! :)
February 11 - Lots of Tyvek, plywood, and roof preparation for a winter storm warning that went south, thank goodness!
January 28 - Installing windows and continuing to cover roof and button up building.
January 16 - Since the end of December wood framing and walls have been placed and as of last week roof framing has started to take shape.
November 19 - Foundation completed this past week, steel has arrived and framing starts next week.
You should see the skeleton of the building start to take shape over the next few weeks.
September 11-17 (Bedford Day) - More foundation prep, dirt removal, gravel added, re-bar delivered.
August 29 - Foundation preparation should commence this week.
Also, good news, the "Moxie" sign has been returned; no reward necessary.
August 17 - Blake Block demolition commenced at 10 AM, complete at 4:20 PM
Demolition went well, but unfortunately part of Bedford's history was taken from the fenced-in site on Wednesday night after the demolition.
We encourage anyone with information as to the whereabouts of the "Moxie" sign (see picture on construction pics page) to call 781-492-2743.
There is a $100 reward for the safe return of the 6'x6' "Moxie" sign.
August 15 - Block demolition schedule changed to Wed (8/17) at 10:00 AM.
August 13 - The construction fence went up this week and block demolition should start on Tuesday (8/16) at High Noon. (We hope, nothing is written in stone, unfortunately!)
August 12 - Demolition scheduled to begin Monday August 15 or more likely on Tuesday August 16.
August 4 - National Grid has shut off the gas, the site is being prepped for demolition, the building inspector, board of health, & DPW did a walk through yesterday & demo permit is just days away from being issued. Once that is done & construction fencing goes up the building can come down.
July 13 - Waiting for Gas Company to disconnect the gas. (10 days - 2 weeks).
July 7 - Trees are down.
April 28 - Start of utility pole removal prep work. T-minus 2 months & counting for projected building completion. Beautiful one- and two-bedroom residential condos for sale on 2nd floor.
For information on premier retail/restaurant space leasing, contact Bruce Blake at 781-492-2743.
April 21 - Another week of beautiful weather & lots of colorful clapboard applied. Progressing by leaps and bounds now!
April 7 - Pole Capping Day & brick front is nearly done with decorative tiles salvaged from old block inlaid around the bend.
March 30 - Brick work, siding, and roofing continues, plus the addition of the corner stone and new signage in front.
March 11 - Spring is around the corner - more windows & doors have been installed - really shaping up!
March 1 - There may be snow outside, but things are moving along inside!
February 18 - More windows, some brick work, and inside framing. It's really coming along! :)
February 11 - Lots of Tyvek, plywood, and roof preparation for a winter storm warning that went south, thank goodness!
January 28 - Installing windows and continuing to cover roof and button up building.
January 16 - Since the end of December wood framing and walls have been placed and as of last week roof framing has started to take shape.
November 19 - Foundation completed this past week, steel has arrived and framing starts next week.
You should see the skeleton of the building start to take shape over the next few weeks.
September 11-17 (Bedford Day) - More foundation prep, dirt removal, gravel added, re-bar delivered.
August 29 - Foundation preparation should commence this week.
Also, good news, the "Moxie" sign has been returned; no reward necessary.
August 17 - Blake Block demolition commenced at 10 AM, complete at 4:20 PM
Demolition went well, but unfortunately part of Bedford's history was taken from the fenced-in site on Wednesday night after the demolition.
We encourage anyone with information as to the whereabouts of the "Moxie" sign (see picture on construction pics page) to call 781-492-2743.
There is a $100 reward for the safe return of the 6'x6' "Moxie" sign.
August 15 - Block demolition schedule changed to Wed (8/17) at 10:00 AM.
August 13 - The construction fence went up this week and block demolition should start on Tuesday (8/16) at High Noon. (We hope, nothing is written in stone, unfortunately!)
August 12 - Demolition scheduled to begin Monday August 15 or more likely on Tuesday August 16.
August 4 - National Grid has shut off the gas, the site is being prepped for demolition, the building inspector, board of health, & DPW did a walk through yesterday & demo permit is just days away from being issued. Once that is done & construction fencing goes up the building can come down.
July 13 - Waiting for Gas Company to disconnect the gas. (10 days - 2 weeks).
July 7 - Trees are down.